02/15/17
|
#17
|
DEPARTMENT OF TRANSPORTATION
|
Authorize the Bureau of Highway Design to amend a contract with Parsons Brinckerhoff Inc., New York, NY, and Manchester, NH, to complete the final design of the roadway and bridges comprising the nort |
$11.6M |
approved
|
|
10/05/16
|
#18A
|
DEPARTMENT OF TRANSPORTATION
|
Authorize the Bureau of Highway Design to amend a contract with Parsons Brinckerhoff Inc., New York, NY and Manchester, NH (originally approved by G&C on 2-20-13, item #88), to complete the final desi |
$11.6M |
approved
|
|
10/05/16
|
#18A
|
DEPARTMENT OF TRANSPORTATION
|
Authorize the Bureau of Highway Design to amend a contract with Parsons Brinckerhoff Inc., New York, NY and Manchester, NH (originally approved by G&C on 2-20-13, item #88), to complete the final desi |
$11.6M |
approved
|
|
10/21/15
|
#22
|
DEPARTMENT OF TRANSPORTATION
|
Authorize the Bureau of Highway Design to amend a contract with Parsons Brinckerhoff Inc., New York, NY, and Manchester, NH (originally approved by G&C on 2-20-13, item #88), to complete the final des |
$11.1M |
approved
|
|
12/03/14
|
#31
|
DEPARTMENT OF TRANSPORTATION
|
Authorize the Bureau of Highway Design to amend a contract with Parsons Brinckerhoff Inc., New York, NY and Manchester, NH (originally approved by G&C on 2-20-13, item #88), to complete the final desi |
$10.3M |
approved
|
|
02/20/13
|
#88
|
DEPARTMENT OF TRANSPORTATION
|
Authorize the Bureau of Highway Design to enter into an agreement with Parsons Brinckerhoff Inc., New York, NY, and Manchester, NH, to complete the final design of the roadway and bridges comprising t |
$9.4M |
approved
|